Time Equals Money: Maximize Efforts to Resolve Project Changes
In the construction industry, the ability to manage change can determine the success or failure of a project’s objectives. The failure to recognize and promptly manage change frequently costs the parties involved money and time. Establishing a change order management process using either contractual change order requirements or a firm’s proprietary system increases the effectiveness of progress reporting, labor productivity evaluation, work scheduling, and other elements of project change. The following steps provide a streamlined approach to resolving project changes in a more cost and time efficient manner:
- Evaluate the contract
- Identify the change properly and in a timely manner
- Provide timely notification to internal and external parties
- Effectively document the change
- Prepare the change request
- Resolve the change request
Implementing these steps at the first sign of a change can help the parties to spend less money and exert less effort to recover or pay for the change costs. As shown in the following diagram, the parties should maximize their efforts to resolve the changes during the project rather than incurring the high costs associated with mediation, arbitration, or litigation.
Step 1: Evaluate the Contract
Rather than relegate the contract to a shelf in the job trailer gathering dust, as often occurs on construction projects, the parties should thoroughly review the contract before the project starts, during the project, and when issues arise, such as drawing revisions, differing site conditions, or project disruptions. In order to identify a change, the parties need to know what the contract considers a compensable change. All of the parties should understand the provisions regarding conflicts and discrepancies in the documents and other risks, such as evaluating the project site, which could affect the entitlement to recover a change. In addition, the contract will provide the proper procedure for processing the change.
Step 2: Identify the Change
The second step is to identify the change, which is defined as any anticipated or actual deviation from the contractual scope, schedule, or cost. One of the most common problems on a project is the contractor or owner’s failure to recognize project change. There are essentially five types of changes:
- Extra/additional work
- Defective/deficient plans/specifications
- Delay and acceleration
- Differing site conditions
- Disruption
Contractors need to ask themselves if a change for extra/additional work is a directed change with an issued formal change order or a constructive change. A constructive change is defined as any conduct by an owner that is not acknowledged by a formal change order but which requires the contractor to perform work that is not mandated by the contract, such as altering the contractor’s methodology, quality, or scheduling of work.
When defective plans and specification issues arise, evaluate the contract language, as it may shift the responsibility to the contractor. The contract may contain a disclaimer regarding the accuracy and completeness of the contract documents or require the contractor to field check dimensions. Specifically, the contract may require the contractor to meet certain performance specifications rather than a particular design. Additionally, the contractor may be viewed as an expert in its field who should possess the required knowledge to determine that the specification was defective.
Contracts can be very specific regarding the types of compensable delays allowed, thus it is important to review the contract for no-damages-for-delay clauses which typically bar the recovery of delay damages. However, even if the contract has a no-damages-for-delay clause, the contractor may still be eligible for delay compensation if the delays were not contemplated by the party, were caused by fraud or bad faith, were of such unreasonable duration that contractor abandonment would be justified, or were caused by active owner interference.
Other time related changes include acceleration and constructive acceleration. While acceleration costs such as additional labor or overtime premiums can be covered by a formal change order, constructive acceleration efforts are not. Constructive acceleration occurs when the contractor is delayed by something that warrants a time extension under the contract but the owner denies the time extension request. The owner also maintains the original completion date or indicates that it will penalize the contractor if it does not meet the schedule. The contractor needs to identify this has occurred and inform the owner that it will accelerate its workforce to recover the delays and will incur acceleration costs. Owners need to be able to identify this type of change, as they may not realize that they have essentially authorized or implied an order to accelerate.
Differing site conditions are also generally addressed in the contract. If changes resulting from differing site conditions are barred by the contract, then evaluate alternative contract support such as directed changes to the work, constructive changes, defective plans and specifications, or misrepresentation.
Another type of change is disruption, which may be caused by a delay, directed or constructive change, lack of action, or a number of other factors such as workspace overcrowding or defective owner-supplied equipment. Disruption increases the level of difficulty in performing the work and the cost of performance. Be aware, however, the damages resulting from disruption can be difficult to quantify and prove, as they involve labor productivity, material costs, or workmanship issues.
Step 3: Notify Internal and External Parties
Notification is the third element in effective change order management. It is both an internal and external function and is critical to identifying when a change occurs and the resulting impact. Notifying the project management/project control teams early allows them the opportunity to more effectively control costs and schedule impacts.
In addition, contractors need to adhere to the required external notification procedures, particularly time constraints. Prompt notice is generally a contract requirement, but even if it is not, contractors should promptly notify the owner of any conditions encountered, such as an unforeseen site conditions, even if there is uncertainty whether there will be a forthcoming change order request. Lack of notice can be a strong defense for owners, and owners should be given an opportunity to seek the most economical course of action in response to a change. This is particularly true if the contractor encounters a constructive change or constructive acceleration. In this situation, the contractor should notify the owner, in writing, that the instruction is considered a change.
Finally, anticipate critical issues as early as possible, since changes can be rejected solely on the failure to meet contractual time limitations. Internal and external notices should be sent promptly without waiting for quantification of time or costs. Timely notice and exchange of information promotes prompt change order resolution.
Step 4: Document the Change
The next step, documenting the change, is a vital construction management function. If profitability depends upon the collection of extras or defense of claims, and the claimant has no records, the world’s best consultants and lawyers will be unable to create them. Or, if the records are in poor shape, the cost of compiling suitable information for the pursuit or dispute of a change order may be high. The most important point about documentation is that it needs be created and in a timely fashion. A comprehensive documentation system provides the data necessary to obtain an equitable resolution when disputes arise. Proving the occurrence of events and causes of problems are key elements in resolving change requests. Negotiations may be held months or years after the work was performed, and those performing the work may not remember details regarding the specific issues or may not even be present during the negotiations. Furthermore, courts and arbitrators tend to give more credence to contemporaneous written documentation than to testimony.
The discipline required for effective documentation requires the same type of management emphasis, instruction, repetition, and follow-up that construction professionals use to ensure that equipment is properly maintained, safe working practices are followed, and reports are submitted on time. Project managers should establish a minimum checklist of records for retention including:
- Diaries
- Daily reports
- Project correspondence
- Meeting minutes
- Schedules
- Cost records
- Photographs
These documents should specifically cite if planned operations are delayed, prevented, or changed in nature. Documents from the other party need to be reviewed carefully for accuracy, and errors or omissions should be promptly corrected in writing. Also, it is critical to have regularly updated schedules at various intervals to identify and quantify the schedule effects of a change. The importance of accurate cost records cannot be over emphasized, as contractors are generally required to demonstrate that they actually incurred the costs because of extra work, delays, or disruptions. When extra work is identified and separable, the associated costs, including labor and material costs as well as equipment utilization, should be recorded under separate cost codes established specifically to quantify it.
Step 5: Prepare the Change Request and Damage Calculation
Different types of changes require different types of supporting documentation and analysis. Change requests should follow the contract requirements and be prepared in a professional manner, well-organized, and neatly presented for review. Additionally, change requests should effectively use graphics and numbers to communicate the desired information to the intended audience and establish a link or cause-effect relationship between the entitlement and the damages. They should include the following elements:
- Factual history with key documents and correspondence
- Entitlement utilizing contract provisions, industry standards, legal statutes, and equity concepts
- Damages utilizing various calculation methods
Using key documents and correspondence is helpful in establishing a factual history regarding the change. Creating a timeline of events or using the project schedule, if possible, is also advisable, as it can illustrate the events leading up to the change as well as any events occurring after notification of the change.
A common weakness in change requests covering complex issues is the absence of provable linkage between the causes of construction claims and their effects. Knowledge of the contract is invaluable in establishing entitlement to damages and reference to applicable industry standards can strengthen the entitlement. Thus, adequate preparation is important to achieve optimal results.
There are different methods used to calculate damages. Change orders may be priced by a contract agreed-upon lump sum price or unit price. If changes are to be calculated by unit prices and the estimated quantities have significantly changed, then the contractor may be entitled to a price adjustment for the performance cost increases. However, the contractor needs to prove that the nature or character of the work significantly changed.
Delay damages are another change order option and generally require a schedule analysis to prove delay periods and associated entitlement. Compensation may include a schedule extension, extended general condition costs and home office overhead, idle equipment costs, and escalation. In addition, the contractor may assert consequential damages such as lost profits on other work.
Productivity loss calculations are another form of damage calculation that address manpower overruns associated with overtime, scope change, poor site conditions, and other construction labor interferences. Productivity losses can be calculated utilizing industry studies such as MCAA, Business Roundtable, CII, or NCAA as references, internal productivity/manpower records, or the court preferred method, the measured mile. The measured mile calculation compares the production rates of an un-impacted time period to an impacted time period for the same work activity. The un-impacted time period serves as the baseline to determine the productivity loss for work that was inefficiently performed.
Two other damage calculation methodologies are total cost and modified total cost. Total cost is where the contractor claims the entire cost overrun as the consequence of the changed condition. For the contractor to assert total cost, the contractor should pass a validity test: the contractor’s costs are accurate and reasonable, the contractor’s bid was reasonable and contained no errors, the contractor was not responsible for the cost overrun, and no other way exists to reasonably calculate the contractor’s damages. The modified total cost approach is used when the total actual cost incurred on the project is less than the estimated cost to perform the job under expected circumstances or there is a need to adjust the difference for any of the contractor’s own faults on the project, such as a bid error or faulty work.
Step 6: Resolve the Change Request
Resolving the change request is the final stage of the process and is perhaps the most frustrating. For cost benefits, both parties should strive to resolve the change request at the negotiation level, as litigation or arbitration are expensive and time consuming. One of the most important decisions in negotiation is deciding who will attend. Depending on the parties’ current relationship status and ultimate goals, owners and contractors need to decide between utilizing the project management team, company managers, or outside consultants.
It is more important, though, to enter the negotiations with the right mind-set. Each party needs a member who knows how to effectively present the position or identify incentives or needs for the other party. The negotiation team should be aware of the situation, from a factual, financial, and legal standpoint. Furthermore, patience is critical, as the negotiations can linger for weeks, months, or years. Members need to deal with roadblocks, such as the opposing side not having qualified or prepared representatives present, rather than becoming discouraged or ignoring the roadblocks. And, finally, if settling the dispute is the number-one priority, then both parties need to be willing to compromise.
By understanding and implementing these change management steps, the chances of the parties resolving the outstanding change orders more effectively and efficiently greatly increase. If these steps are implemented in a timely manner, the parties are more likely to resolve the changes during the project as opposed to during mediation, arbitration, or litigation, which is the most costly option for all parties involved.
Source: Interface Consulting International, Inc.